Standard System Installation
Eaton BladeUPS 5.1 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 9 www.eaton.com/powerquality 73
The UPS requires a dedicated branch circuit that meets the following requirements:
l
Circuit with overcurrent protection as follows:
- 50A (BladeUPS 12 model)
- 30A (BladeUPS 12i or BladeUPS 8 model)
- 20A (BladeUPS 5.1 model)
l
Three-phase, 4-wire plus ground, 208Y/120V nominal (BladeUPS 12 model) with 5-pin IEC309-60 amp
receptacle or in-line connector (GH560C9W or similar).
l
Three-phase, 4-wire plus ground, 400Y/230V nominal, (380–415 Vac acceptable), (BladeUPS 12i model) with
5-pin IEC309-30 amp receptacle or in-line connector, (GH532C6W or similar)
l
50/60 Hz
l
Wall-mounted breaker that is readily accessible to the operator
The BladeUPS models require the following input plug and receptacle (see Table 8):
To install the UPS:
1. Switch off utility power to the distribution point where the UPS will be connected. Be absolutely sure
there is no power.
2. Verify that all circuit breakers are in the OFF (O) position.
3. If you are installing power management software, connect your computer to the UPS communication port
or optional X-Slot card (see
“Installing Communication Options and Control Terminals” on page 108). For
the communication port, use the supplied serial cable.
4. If your rack has conductors for grounding or bonding of ungrounded metal parts, connect the ground cable
(not included) to the ground bonding screw. See
Figure 60 for the location of the ground bonding screw.
5. If an emergency power-off (disconnect) switch is required by local codes, see “Remote Emergency
Power-off” on page 112 to install the REPO switch before powering on the UPS.
6. Plug in UPS plug into provided utility input receptacle or connector
7. Plug power distribution (RPM or ePDU), into BladeUPS output connector or load connector.
8. Continue to “Standalone UPS Initial Startup” on page 88.
Table 8. Required Plugs and Receptacles
BladeUPS Model Input Plug Receptacle
12i kVA IEC309-32 (GH532P6W or similar) GH532C6W (or similar)
12 kVA IEC309-60 (GH560P9W or similar) GH560C9W (or similar)
8 kVA NEMA L21-30P NEMA L21-30R
5.1 kVA NEMA L21-20P NEMA L21-20R
NOTE The load connector breaker controls the load connector only, not the output power
cord.